Building our Winter Village


The weather hasn't quite caught up to us, but we're moving right along with preparations for the Bank of America Winter Village at Bryant Park! We want to make sure we're all buttoned up and ready to open on November 1, so there isn't a moment to waste. Crews are working hard to build floors, walls and roofs for each of the Holiday Shops. They've also laid the foundations for the ice rink and surrounding deck. In the northeast corner of the lawn, you can see the steel beams that will support our pop-up restaurant Celsius. Thank you for your patience as we build these winter amenities.

Share your excitement with photos of the load-in. Be sure to tag #WinterVillage throughout the season, so we can see things from your view!